2018 Storm Drain Rehabilitation Project

Print
Press Enter to show all options, press Tab go to next option

The City of Lafayette awarded a contract to Kerex Engineering, Inc. in the amount of $318,183.00 to remove and replace or rehabilitate existing storm drain pipes on multiple streets in Lafayette this summer. 

 Pipe reconstructions are planned at the following locations:

Legion Court - on private property
Mosswood Drive - on private property
Village Center at Mosswood Drive
School Street at Avalon Court
St. Mary's Road - south of Burton Court
Mt. Diablo Boulevard - between Hampton Road & Aileen Street
Old Tunnel Road - between Linda Vista Lane & Windsor Drive
Quandt Road at Candy Court.

Work began on July 23rd, with an anticipated completion date for the entire project in September.  Weekly progress reports can be accessed via the link below:

Weekly Update

 

Other project information:

Resident Notification Letter, 7/9/18

   

BID DOCUMENTS & INFORMATION 

Bid Opening Results

Bids Comparison Spreadsheet

Project Specifications

Project Plans