The contractor has continued to prepare the site for construction.
Next week the contractor plans on starting the following:
- Start of demolition of existing improvements
- Tree removal in the vicinity of the new Bike Station.
The working hours for this project are 7:30 am to 4:30 pm Monday through Friday. Emergency vehicles will always be provided with access.
Questions regarding this project may be directed to Matt Luttropp, Engineering Services Manager at 925-299-3247 or via email. Background on the project is available on our website.