After last week’s rain, the contractor let the site dry out before spending this week continuing to work on the foundation for the new Bike Station.
Next week the contractor plans to work on the following:
- Continue work on the bike station foundation
- Begin grading for the new walkway and ramp in front of the bike station
The working hours for this project are 7:30 am to 4:30 pm Monday through Friday. Emergency vehicles will always be provided with access.
Questions regarding this project may be directed to Matt Luttropp, Engineering Services Manager at 925-299-3247 or via email. Background on the project is available on our website.