Press Releases

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

BART Bike Station/Pathway Project Update, May 29, 2026

Post Date:05/29/2026 10:09 AM

The rain on Thursday pushed back the concrete pour for the bike station foundation and slab.  The contractor began placing formwork for the curb wall.

 For the week of June 1, the contractor plans to work on the following:

  • Pour concrete foundation and slab for the bike station.
  • Continue forming the concrete curb wall.
  • Continue grading for the new walkway and ramp in front of the bike station.

The working hours for this project are 7:30 am to 4:30 pm Monday through Friday.  Emergency vehicles will always be provided with access.

Questions regarding this project may be directed to Matt Luttropp, Engineering Services Manager at 925-299-3247 or via email. Background on the project is available on our website.

 

Return to full list >>