The curb wall behind the bike station foundation was poured on Monday. The contractor began placing storm drain and forming for storm drain inlets.
For the week of June 15, the contractor plans to work on the following:
- Storm drain pipe and inlet installation.
- Backfill and form new light pole foundation in front of bike station.
- Continue grading for the new walkway and ramp in front of the bike station.
- Begin installing sleeves for irrigation.
The working hours for this project are 7:30 am to 4:30 pm Monday through Friday. Emergency vehicles will always be provided with access.
Questions regarding this project may be directed to Matt Luttropp, Engineering Services Manager at 925-299-3247 or via email. Background on the project is available on our website.