Press Releases

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

BART Bike Station/Pathway Project Update, June 26, 2026

Post Date:06/26/2026 1:22 PM

The irrigation sleeves in front of the bike station were installed and the concrete was poured for drainage inlets and a light pole foundation.  The contractor began forming the curb, gutter and curb ramp.

For the week of June 29, the contractor plans to work on the following:

  • Backfill irrigation sleeve trench and storm drain trench.
  • Complete the formwork for the curb, gutter, and ramp in front of the bike station, compact subgrade, and install slurry cement base.

The working hours for this project are 7:30 am to 4:30 pm Monday through Friday.  Emergency vehicles will always be provided with access 

Questions regarding this project may be directed to Matt Luttropp, Engineering Services Manager at 925-299-3247 or via email. Background on the project is available on our website.

Return to full list >>