Press Releases

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

BART Bike Station/Pathway Project Update, July 17, 2026

Post Date:07/17/2026 10:10 AM

The contractor continued to demolish the existing asphalt concrete and began grading the subgrade for the roundabout area.

For the week of July 20, the contractor plans to work on the following:

  • Pour concrete curb, gutter, sidewalk, and curb ramp in front of the bike station.
  • Grade and compact the subgrade in preparation for the slurry cement.

The working hours for this project are 7:30 am to 4:30 pm Monday through Friday.  Emergency vehicles will always be provided with access.

Questions regarding this project may be directed to Matt Luttropp, Engineering Services Manager at 925-299-3247 or via email. Background on the project is available on our website.

Return to full list >>