The contractor continued to grade and compact the subgrade for the roundabout area, began to demolish concrete surfacing, and excavate for the art poles and storm drain.
For the week of August 3, the contractor plans to work on the following:
- Trench and install storm drain.
- Drill for art pole foundations.
- Trench and install electrical conduit and irrigation sleeves.
- Begin forming concrete curbs and bands.
The working hours for this project are 7:30 am to 4:30 pm Monday through Friday. Emergency vehicles will always be provided with access.
Questions regarding this project may be directed to Matt Luttropp, Engineering Services Manager at 925-299-3247 or via email. Background on the project is available on our website.