BART Bike Station/Pathway Project Update, August 14, 2026

Post Date:08/14/2026 1:14 PM

The contractor installed the reinforcing steel and formwork for two art pole foundations. 

For the week of August 17, the contractor plans to work on the following:

  • Install electrical conduit to art pole foundations.
  • Pour concrete for art pole foundations.
  • Trench and install storm drain.
  • Trench and install electrical conduit and irrigation sleeves.
  • Begin forming concrete curbs and bands.

The working hours for this project are 7:30 am to 4:30 pm Monday through Friday.  Emergency vehicles will always be provided with access.

Questions regarding this project may be directed to Matt Luttropp, Engineering Services Manager at 925-299-3247 or via email. Background on the project is available on our website.