On May 28, 2019, the City of Lafayette awarded a construction contract to VSS International, in the amount of $1,586,000, for maintenance repairs, ranging from patch paving and crack sealing to chip seal and/or slurry seal treatments, on the following streets over the summer:

    Street:                                                      From:                                                        To:

Birdhaven Ct

St Mary's Rd

End

Broadmoor Ct 

St Mary's Rd

End

Carolyn Ct

Meek Pl

End

Crestmont Dr 

Happy Valley Rd

End

Dyer Dr

Hampton Rd

End

Hawthorne Dr

Diablo Dr

Upper End

Hoedel Ct

N Buchan Dr

End

Lindsey Ct

N Buchan Dr

End

Meadow Ln

Franklin Ln

Rose Ln

Oak View Cir

Hawthorne Dr

End

Olympic Blvd

Pleasant Hill Rd

Reliez Station Rd

Ridge Rd

Hawthorne Dr

End

Santa Maria Ct

Santa Maria Way

End

Santa Maria Way

St Mary's Rd

End

Second St Mt Diablo Blvd 

 End (N)

Work includes:  mobilization; traffic control and construction signage; clearing and grubbing including tree trimming; traffic striping, marking and marker removal; removal and replacement of concrete sidewalk, curb ramps, curb and gutter; construction of asphalt concrete pavement repairs; crack seal; rubberized chip seal; micro-surfacing; traffic stripes, markers, and markings; and all other work as shown on the plans and as described in the Specifications to provide a complete project.

Once construction begins, a weekly project update will be available via a link on this page. 

 

BIDS OPENED:  Wednesday, May 15, 2019, 2:00 PM 

BID RESULTS

BIDS COMPARISON SPREADSHEET

 

BID DOCUMENTS & INFORMATION:

Plans & Specifications 

Addendum #1 issued 5/13/19